Quick answer: at CCS Builders, a basement built as part of a new home starts from around $290,000. Digging a new basement under an existing house costs much more: a 100m² living-space basement typically costs $550,000–$950,000 in total, about $6,000–$9,000 per m², mainly because the house has to be underpinned while the ground beneath it is excavated. Rock, groundwater, depth and how close you build to the boundary decide where your project falls.
The new-home starting price is CCS Builders’ own pricing. The existing-house figures are indicative 2026 Sydney market ranges from published cost guides. Neither is a quote: we price every job from your plans and geotechnical report.
Basement under an existing house
This is the most expensive way to build a basement, because the house has to be supported (underpinned) while the ground beneath it is excavated. Published 2026 Sydney guides put typical costs at:
- Geotechnical report: about $6,000–$14,000
- Underpinning: about $3,500–$7,000 per linear metre of wall
- Bulk excavation in sandstone: about $180–$450 per m³
- Tanking (waterproofing) and drainage: about $180–$350 per m² of below-ground wall and floor
- Structure and fit-out: about $2,800–$4,500 per m² for habitable space
- Engineering and inspections: about $15,000–$40,000
Added together, digging a new 100m² living-space basement under an existing house typically costs $550,000–$950,000 in total, or about $6,000–$9,000 per m². Other Sydney basement specialists quote similar figures of around $6,000–$7,000 per m².
Basement as part of a new home: from $290,000
CCS Builders’ new-home basements start from around $290,000. The final price depends on size, depth, rock, shoring and whether the space is a garage or fitted out as living space.
When you knock down and rebuild, or build on a vacant block, the basement is excavated before the house goes up. There is no underpinning, machinery access is easier and the basement shares footings and slabs with the home above. That makes it far cheaper per square metre than a retrofit basement, and it is the most cost-effective way to add a garage, cellar, gym or media room.
The biggest cost variables on a new-home basement are:
- Rock: soil can be cut and carted cheaply, but rock that needs hammering can cost several times more per m³.
- Shoring near boundaries: excavating close to a neighbour usually needs piling or shoring walls designed by an engineer.
- Groundwater and waterproofing: sites with a high water table need full tanking and sometimes a pump-out system.
- Driveway ramp: grades and retaining for basement car access.
- Spoil disposal: tip fees depend on the volume and whether the soil is classified as clean.
What pushes a basement price up
- Sandstone or shale that needs rock breaking or saw-cutting
- Tight access, for example a narrow side passage or no truck access
- Excavating right up to a boundary or next to an old neighbouring building
- Groundwater or flood-affected land
- Habitable fit-out (bathroom, kitchenette, home theatre) rather than a garage
- Council conditions, such as extra reports or monitoring during excavation
How to get an accurate basement price
- Get a geotechnical report early. It tells you about rock and groundwater, the two biggest unknowns.
- Have the structure engineered before you finalise the budget. Shoring and retaining design changes the price more than finishes do.
- Ask for rock and spoil to be priced clearly. Many quotes exclude rock or list it as a separate rate, so check yours.
- Plan approvals at the same time. Most basements need a DA. See our guide to basement and pool approvals in NSW.
Talk to a Sydney basement builder
CCS Builders builds basements and new homes with a basement and pool across Sydney, managing excavation, engineering, waterproofing and approvals under one contract. Send us your plans or site details for a tailored estimate.
Frequently asked questions
How much does a basement cost in Sydney?
A basement built as part of a new home starts from around $290,000 with CCS Builders. Digging a new basement under an existing house typically costs $6,000–$9,000 per m², or $550,000–$950,000 for a 100m² living-space basement.
Is it cheaper to build a basement with a new home?
Yes, much cheaper. Without an existing house to underpin, excavation is simpler and the basement shares structure with the home above. Our new-home basements start from around $290,000.
Does rock make a basement more expensive?
Usually, yes. Rock excavation can cost several times more per cubic metre than soil, which is why a geotechnical report should come before the final price.
How long does a basement take to build?
It depends on size, rock and approvals. Excavation and structure are usually the longest stages, and they happen before the rest of the house can start.